October 2004 Coll awarded Initiative at the Edge status. In the months that follow, a board of volunteer directors is formed
June 2005 Community consultation carried out with a questionnaire going to all households
Oct 05 Local Development Officer appointed
Jan 2006 Community Gathering to discuss the results of the questionnaire
Feb 2006 Postal vote held to ratify the Development Plan
May 2006 Public meeting held to discuss future of the current Hall: unanimous decision to pursue the option of a combined new facility with the Education Dept. A working group is established to progress this project.
April 07 Receive funding from the Lottery to develop our ideas under the Lottery’s Growing Community Assets fund. This funding will include the hiring of an architect for the initial design and community consultation.
Oct 07 Competition run to choose an architect to take the project forward
Nov 07 Anderson Bell Christie are appointed as the architects
Jan-March 2008 Rounds of Community consultation for design of building. A design is agreed upon.
Mid March 08 Outline Proposal Form submitted to the Lottery
End March 08 We are invited by the Lottery to submit a full application. Our case officer indicates that for the Growing Community Assets fund, circa 35% of groups are invited to submit a full application following their Outline Proposal Form
23rd May 08 The planning application was submitted to Oban Planning Department
25th July 08 The planning application approved
Sept 08 Full application is due to the lottery, funding profile needs to be in place
Jan 09 We will hear back from the Lottery, and progress accordingly!
|